How an Extraction Canopy Is Installed: From Survey to Commissioning

How a commercial extraction canopy goes from survey to commissioning: measuring, fabrication, fixing, ductwork connection, make-up air, testing and hand-over.

How is a commercial kitchen extraction canopy installed?

Installation follows a sequence: site survey and drawings, fabrication to measure, fixing the canopy to the structure, connecting ductwork and the extract fan, balancing make-up air, testing any gas interlock and commissioning the airflow. Doing it in the right order, with the services trades coordinated, is what avoids rework.

Last updated

Canopies13 Nov 20267 min read
How an Extraction Canopy Is Installed: From Survey to Commissioning

Step 1: survey and design

We meet you or your architect, visit the premises and measure the kitchen. We then produce proposed scheme drawings, including any filtration systems required and odour control. This is where canopy size, duct route, fan position and make-up air are agreed, and where planning and Environmental Health requirements are considered.

Step 2: coordinate with other trades

A canopy touches many other trades: gas, electrics, plumbing, structure, fire and the fit-out. We attend design meetings and liaise with the architect, structural engineers, other services, the developer and the Environmental Health Officer. Good coordination at this stage prevents clashes on site, such as a gas pipe where the canopy needs to be.

Step 3: fabrication to measure

Canopies are fabricated to measure at our own works from 304 stainless steel, then delivered. Measuring accurately before fabrication matters because a canopy cannot easily be trimmed on site without damaging the finish.

Step 4: fixing and connection

The canopy is lifted into position and fixed to the structure. The ductwork is connected to the canopy collar, and access doors are fitted for cleaning. Ducts are built to DW/172; see kitchen extract ductwork. Grease filters are fitted in the canopy housing.

Step 5: make-up air and gas interlock

HSE guidance in the catering ventilation sheet says the system design should take account of the need to replace extracted air. The make-up air is connected and balanced against the extract. Where gas appliances rely on the extraction, a gas interlock is fitted by a Gas Safe registered engineer and tested.

What can delay a canopy installation

Most delays are avoidable. Late decisions about appliances change the canopy size; gas, electrical or structural work that has not been coordinated means the canopy cannot be fixed; planning conditions that were not discharged hold up the duct; and access problems, such as a narrow stairwell or restricted delivery hours, slow the lift. Tell us early about trading hours, access, landlord rules and any approvals you are waiting for, and we will build them into the programme. For a wider view of timing, see our opening a restaurant checklist.

Step 6: commissioning and hand-over

Airflow is measured and adjusted, safety devices are tested and the canopy is checked for spillage with appliances running. HSE advises keeping records of design criteria, commissioning performance and maintenance requirements (CAIS10). You receive those records, and we can set up planned maintenance.

See also extraction canopies and the full kitchen extraction service.

Frequently asked questions

How long does canopy installation take?

It depends on the size, duct route and site. We give a programme with the quotation.

Can you install a canopy out of hours?

Often yes. Tell us about your trading hours at survey.

Do I need other trades on site?

Usually gas, electrical and sometimes structural work. We coordinate with them.

Who tests the gas interlock?

A Gas Safe registered engineer, as part of commissioning.

What records do I get at the end?

Commissioning results and maintenance requirements, so the system can be checked against its design later.

Need this sorted on site?Talk to our team: survey, quote and install anywhere in the UK.
Call 07759 696007
Keep reading

More from the blog

Planning a kitchen or air conditioning project?

Tell us where your site is and what you need. We survey, design, manufacture, install and maintain across the UK.

WhatsApp us
Call Now Get Quote